Skip to main content

Illumio Core 25.2.10 Install, Configure, Upgrade

Post-Migration Tasks

If you encountered problems during migration and need to recover from any failures. In this case, read the following troubleshooting section.

Complete the Migration

After migrating all VENs, retire the on-prem PCE, remove API keys, and remove any unnecessary workloads on SaaS.

Review this checklist to ensure you have completed the migration of VENs to SaaS PCE.

Table 10. Standard Post-migration Tasks

Category

Required Status

Action

Unmanaged workloads

Unmanaged workloads have been removed.

Run the pcemigrate sync command to clean up unnecessary workloads.

On-premise PCE

The on-premise PCE was properly decommissioned after the VENs were migrated.

  • Retire the on-premise PCE.

  • Delete the API keys generated during the migration.

  • Remove unnecessary unmanaged workloads from the Illumio SaaS.